The example uses VPP interface with attached route to outline the control-flow of item re-creation. A specific configuration update may not be supported by SB to perform incrementally - instead the given item may need to be deleted and re-created with the new configuration. Using UpdateWithRecreate() method, a descriptor is able to tell the KVScheduler if the given item requires full re-creation for the configuration update to be applied.

This example demonstrates re-creation using a VPP TAP interface and a NB request to change the RX ring size, which is not supported for an already created interface. Furthermore, the interface has an L3 route attached to it. The route cannot exists without the interface, therefore it must be deleted and moved into the PENDING state before interface re-creation, and configured back again once the re-creation procedure has finalized.

CFD

<< Back to control flow diagram index